Job 593 was recently completed. The following data have been recorded on its job cost sheet:


Direct materials $2,461
Direct labor-hours 74 labor-hours
Direct labor wage rate $ 18 per labor-hour
Machine-hours 137 machine-hours


The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $19 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:

$3,720
$3,793
$7,236
$6,396

Respuesta :

Answer:

$6,396

Explanation:

The total cost that would be recorded on the job cost sheet for Job 593 would be $6,396

Direct materials= $2,461

Direct labor-hours= $1,332 (74 labor hours= $18 per labor-hour= $18*74 labor-hours= $1,332)

Machine-hours= $2,603 (137 labor hours= $19 per machine-hour= $19*137= 2,603)

To find the total, we add all the numbers.

$2,461+$1,332+$2,603= $6,396

Therefore the total cost that would be recorded on the job cost sheet for Job 593 would be $6,396.