Answer:
price variance $3,300.00
quantity variance $(3,450.00)
rate variance $(500.00)
efficiency variance $(3,225.00)
Explanation:
DIRECT MATERIALS VARIANCES
[tex](standard\:cost-actual\:cost) \times actual \: quantity= DM \: price \: variance[/tex]
std cost $2.30
actual cost $2.10
quantity 16,500
difference $0.20
price variance $3,300.00
[tex](standard\:quantity-actual\:quantity) \times standard \: cost = DM \: quantity \: variance[/tex]
std quantity 15000.00
actual quantity 16500.00
std cost $2.30
difference -1500.00
quantity variance $(3,450.00)
DIRECT labor VARIANCES
[tex](standard\:rate-actual\:rate) \times actual \: hours = DL \: rate \: variance[/tex]
std rate $7.50
actual rate $8.50 (4,250 / 500 hours)
actual hours 500
difference $(1.00)
rate variance $(500.00)
[tex](standard\:hours-actual\:hours) \times standard \: rate = DL \: efficiency \: variance[/tex]
std hours 70.00
actual hours 500.00
std rate $7.50
difference -430.00
efficiency variance $(3,225.00)