A company can complete a certain job in 12 days, another company can complete the same job in 9 days, and the third company in 18 days. In how many days can three companies, if they work together, complete the job?

Respuesta :

Answer:

4 days.

Explanation:

Given:

A company can complete a certain job in 12 days.

Another company can complete the same job in 9 days,

And the third company in 18 days.

Question asked:

In how many days can three companies, if they work together, complete the job ?

Solution:

In 12 days, a company can complete = 1 job

In 1 day,  a company can complete = [tex]\frac{1}{12}[/tex] of the job ( one - twelfth part of the job)

Similarly, another  company can complete in 1 day = [tex]\frac{1}{9}[/tex] of the job

And the third company can complete in 1 day = [tex]\frac{1}{18}[/tex] of the job

Now, to find number of days they will take to complete the whole job together,

In 1 day, all the three company can complete = [tex]\frac{1}{12}+\frac{1}{9} +\frac{1}{18}[/tex] of the job        

By taking LCM of 12, 9 and 18 we get 36         =[tex]\frac{3+4+2}{36} =\frac{9}{36} = \frac{1}{4}[/tex] of the job  

Now, [tex]\frac{1}{4}[/tex] of the job is done in = 1 day

Then the 1 whole job is done in = [tex]\frac{1}{\frac{1}{4} }[/tex]   ( by unitary method )                                                      

                                                     = [tex]1\div\frac{1}{4}[/tex]

                                                     = [tex]1\times\frac{4}{1} = 4 \ days[/tex]

Therefore, three companies can  complete the job in 4 days, if they work together.

Answer:

4 days require three companies to complete the job

Explanation:

Let

One company be A, another be B and third be C

Work done by A in 1 day = 1 / 12 days

Work done by B in 1 day = 1/ 9 days

Work done by C in 1 day = 1/ 18 days

So,

Work done by all three companies will be computed as:

A + B + C = 1/ 12 + 1/ 9 + 1/ 18

Taking the LCM of 12, 9, 18  , which comes 216

= 18 + 24 + 12 / 216

= 54 / 216

Now dividing 54 by 216, it will be:

= 1 / 4 days or 4 days

Therefore, the work done by all companies is 1/ 4 days, which means they need 4 days to complete the job.