Answer:
1.0
Explanation:
Benefit-cost ratio BCR can be expressed in monetary or qualitative terms. It presents the relationship between the relative costs and benefits of a proposed project.
If a project has a BCR greater than 1.0, the project is expected to be attractiveto a firm and its investors.
If a project's BCR is less than 1.0, the project's costs outweigh the benefits, and it should not be considered because it is unattractive.