PERT refers to Program Evaluation and Review Technique, which was developed in the 1950s to better understand how variability in the individual activity durations impacts the entire project schedule.a) trueb) false

Respuesta :

Answer:

A) True

Explanation:

The PERT chart was first developed by the US Navy to manage the Polaris submarine missile program. As other military developments (like the internet), it later passed into the business world. It is project management tool used to analyze and represent the activities in a project. It also helps to track down the flow of events of a project and to estimate the time to completion.