Answer:
The materials and supplies in the flexible budget for August would be closest to: $44
Explanation:
Given that actual materials and supplies cost: $2,250.
As we know that, the flexible supplies cost equal:
= 54 vehicles ×$4 + $1,990
= $216 + $1,990
= $2,206
The computation of the spending variance is:
= $2,250 - $2,206
= $44
So the materials and supplies in the flexible budget for August would be closest to: $44