Respuesta :
Answer:
A.Given this set of daily service operations, and assuming a processing order of A-B-C-D-E: Service Operation Number of Daily Reps A 32 B 24 C 32 D 28 E 12 a. Give one reason that each arrangement might be preferred over the other. b. Determine the number of repetitions for
B.
Step-1: Calculate the units to be processed in one cycle by dividing the daily requirement with number of cycles
Step-2: Assign units per cycle to each cycle
Step-3: Adjust it to accommodate the fractions
C.
Step-1: Calculate the units to be processed in one cycle by dividing the daily requirement with number of cycles,
Step-2: Assign units per cycle to each cycle
The repetitions for each service if two cycles
Explanation: tables in attached file are for questions B and C respectively


Answer:
Explanation:
(a) The reason why each arrangement might be preferred over the other depends on the operation plan. Bigger plan, bigger arrangement and vise versa.
(b)
The number of repetition is calculated in the table below
Service Operation No. of daily reps No. of cycles Reps per cycle
A 32 4 32/4 = 8
B 24 4 24/4 = 6
C 32 4 32/4 = 8
D 28 4 28/4= 7
E 12 4 12/4= 3
The number of repetition per cycle can then be expressed as;
Service Operation Cycle 1 Cycle 2 Cycle 3 Cycle 4
A 8 8 8 8
B 6 6 6 6
C 8 8 8 8
D 7 7 7 7
E 3 3 3 3
(c) The same process is used with two cycles
Service Operation No. of daily reps No. of cycles Reps per cycle
A 32 2 32/2 = 16
B 24 2 24/2 = 12
C 32 2 32/2 = 16
D 28 2 28/2= 14
E 12 2 12/2= 6
The number of repetition per cycle can then be expressed as;
Service Operation Cycle 1 Cycle 2
A 16 16
B 12 12
C 16 16
D 14 14
E 6 6