A key resource is assigned on multiple tasks that are running simultaneously. The project manager needs to minimize impact on activities by delaying activities with the highest values first. The project manager is using ______.

Respuesta :

Answer: Resource levelling

Explanation:

Resource levelling is a term used in project management defined and is defined as a technique used where there is adjustment in the start and finish dates based on limitation in resources with the aim of balancing the demand for resources using the available supply.

While performing activities in project planning, the manager will try to schedule some tasks simultaneously. Resource leveling can be used to balance the workload of the main resources during the duration of of the project usually at the expense of either the time, cost or scope.

Answer:

Resource levelling.

Explanation:

Resource levelling is defined as a project management technique in which start and finish dates of a project are adjusted because of resource constraints. This aims to balance demand for resources with available supply.

For example when resources sucha s machines or people are not available, the project manager needs to adjust schedule to account for non availability of these resources.

So when a project manager minimize impact on activities by delaying activities with the highest values first, he is using resource levelling.