Answer:
a. Capacity required
1776600 minutes per year
b. Total operating time available 264000 minutes per year
c. Assembly cells required 7.00cells
Explanation:
A. capacity required= sum of demand + processing time
B. Number of shifts x hours of shifts x days if shift.
C. Assembly cells = total time required/ total time available in a year