Respuesta :
Answer:
The company should accept Project B because it generates more value per year as compared to Project A.
Explanation:
Explanation can be seen in the file attached.
Answer:
Choose Project A
Explanation:
To choose between two mutually exclusive projects we will use two approaches NPV approach .
Under NPV accept project if NPV is positive and has higher NPV.
Project A NPV
-80 000 + 25000/1.12+25000/1.12^2+25000/1.12^3+25000/1.12^4+25000/1.12^5+25000/1.12^6 = -80000+22321.43+19929.85+17794.51+15887.95+14185.67+12665.78
=$22,785.19
Project B NPV
- 80 000 + 60000/1.12 ^1+60000/1.12^2 = $21,403.06
Choose A as it has higher NPV.