Answer:
The discount rate for this project is 5%.
Explanation:
The discount rate for the new project will be the required rate of return or the cost of equity that will be used to discount the cash flows from the project to calculate its Net present value. Using the CAPM, we can calculate the required rate of return (r) as:
r = rRF + beta * rpM
Where,
r = 2% + 0.5 * 6% = 0.05 or 5%