JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,200,000. JRE2 recognizes revenue upon contract completion. Cost incurredEstimated Cost to Complete 2020$250,000 $1,550,000 2021 1,600,000 500,000 2022 450,000 0 In 2021, JRE2 would report gross profit (loss) of:

Respuesta :

Answer: $(150,000)

Explanation:

Under the Revenue upon Contract Completion method revenue for 2021 is calculated as follows.

The total cost for 2021 will be the cost incurred that year plus that of the previous year which would be,

= 250,000 + 1,600,000

= $1,850,000

We will then add the estimated cost left to find out the total ESTIMATED cost as at 2021,

= 1,850,000 + 500,000

= $2,350,000 is the total estimated cost.

Total Income therefore will be,

= Revenue - Total Estimated Cost

= 2,200,000 - 2,350,000

= -$150,000

JRE2 would report gross LOSS of $150,000 in 2021