The _____ lists the relative probability of a risk occurring and the relative impact of the risk occurring.
a.
Top Ten Risk Item Tracking chart
b.
requirements traceability matrix
c.
probability/impact matrix
d.
expectations management matrix

Respuesta :

Probability / impart matrix lists the relative probability of a risk occurring and the relative impact of the risk occurring

Explanation:

Probability impact matrix:

  • As the name suggests, it is a combination of both probability as well the impact scores of individual risk.
  • Then it prioritize or rank those risks

Top Ten Risk Item Tracking: This tool helps to identify and maintain an awareness of  risks throughout the life of a project

Requirements traceability matrix: This relates two co-baseline documents and check the completeness of the relationship

Expectations management matrix: Project Manager uses this tool to identify the variables viz. scope, budget and schedule and find which is more flexible than the other variables