The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data.

a.The daily demand is 1,700 units.
b.The production lead time is 2 days (this includes processing time, transport time, and waiting time).
c.Management has decided to have 2 day(s) of safety stock
d.One container fits 350 units

How many kanban containers will be needed to support this system?

Respuesta :

Answer:

19

Explanation:

Daily demand (d) = 1700 units

Lead time (L) = 2days

Demand during lead time = d x L = 1700x2 = 3400

Safety stock = 2 days

Safety stock level = d x 2 = 1700x2 = 3400 units

Container size = 350 units

Kanban needed = (demand during lead time + Safety stock level) / container size

= (3400+3400)/350

= 19.4 or rounded to 19 containers