Answer:
19
Explanation:
Daily demand (d) = 1700 units
Lead time (L) = 2days
Demand during lead time = d x L = 1700x2 = 3400
Safety stock = 2 days
Safety stock level = d x 2 = 1700x2 = 3400 units
Container size = 350 units
Kanban needed = (demand during lead time + Safety stock level) / container size
= (3400+3400)/350
= 19.4 or rounded to 19 containers