Respuesta :
Answer:
Explanation:
the solution is shown in the picture attached below

Northern Plant has a variable cost are "[tex]\$ 32,500\ and\ \$210,000[/tex]" and Southern Plant pays variable costs that are "[tex]\$12,500\ and \ \$90,000[/tex]", and calculation can be defined as follows:
Cost calculation:
For questions 1 and 2:
Northern Plant Southern Plant Total
Variable Cost Charges;
[tex]\$0.25 per\ ton \times 130,000\ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$32,500\\\\ \$0.25 per\ ton \times 50,000 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \database \ \ \valie\ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$12,500 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$45,000[/tex]
Fixed Cost Charges:
[tex]70\% \times 300,000 \ \ \ \ \ \ \ \ \ \ \ \ \ \$210,000\\\\[/tex]
[tex]30\%\times \$300,000 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$90,000 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$300,000[/tex]
[tex]\text{Total Charges} \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$242,500 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$102,500 \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \$345,000[/tex]
For question 3:
The spending Variance [tex]=\ \$19,000[/tex]
calculation:
Cost of variable Fixed Cost Total
Total Actual Cost Incurred [tex]\$54,000 \ \ \ \ \ \ \ \ \ \ \ \ \ \$310,000\ \ \ \ \ \ \ \ \ \ \ \ \ \$364,000[/tex]
Total Charges [tex]\$45,000\ \ \ \ \ \ \ \ \ \ \ \ \ \$300,000\ \ \ \ \ \ \ \ \ \ \ \ \ \$345,000[/tex]
Variance Spending [tex]\$9,000\ \ \ \ \ \ \ \ \ \ \ \ \ \$10,000 \ \ \ \ \ \ \ \ \ \ \ \ \ \$19,000[/tex]
Find out more about the cost calculation here:
brainly.com/question/15161633