Answer:
$2,295.
Explanation:
Note: The data in the question are merged together and they are first sorted before the question is answered as follows:
Job # Total Cost Complete? Sold?
803 $500 yes yes
804 200 yes no
805 900 no no
806 600 yes yes
807 400 no no
808 380 no no
809 600 yes no
810 680 yes yes
811 225 no no
812 390 no no
The following is now the explanation to the answer:
To calculate the total in the work-in-process (WIP) account, we add the total costs of jobs in the table above not yet completed as follows:
Total in the work-in-process (WIP) account = $900 + $400 + $380 + $225 + $390 = $2,295.