Answer:
The answer is 12,000
Explanation:
Solution
Given that:
The labor rate variance = (SR-AR) * AH
Now,
(15-13.50) * AH = 18,000
so,
AH= 18000/1.50
Gives us,
=12,000
The total labor variance is = The standard labor cost - The actual labor costs.
= (10000* 15)- (12,000 * 13.50)
=150,000 -162,000
= 12,000 U
Therefore the total labor variance Claire Company is 12,000