Answer:
A, B, and D.
Explanation:
According to the situation, computation of the given data is shown below:
We'll need to evaluate the WACC with the expected return, to figure out which project set would maximize the wealth of the shareholder.
Particular Risk WACC(required return) (%) Expected Return (%) Accept or Reject Reason
Project A High 12 15 Select WACC is lower than expected return.
Project B Average 10 12 Select WACC is lower than expected return.
Project C High 12 11 Reject WACC is higher than expected return.
Project D Low 8 9 Select WACC is lower than expected return.
Project E Low 8 6 Reject WACC is greater than expected return.
As per the analysis, option C (project A,B and D) should be selected to maximize shareholder’s wealth.