Respuesta :
Answer:
Explanation:
From the question; in regard with the material requirements plan MRP for the item Z; we have the following constructed table:
Item Z 1 2 3 4 5 6 7
Gross 120
Requirement
On-hand = 40
Schedule reciept
Balance 40 40 40 40 40 40 -
Net requirement 80
Planned Order
Receipt 80
Planned Order
Release 80
Following the material requirements plan (MPR) for A.
Item A 1 2 3 4 5 6 7
Gross 160
Requirement
On-hand = 70
Schedule reciept
Balance 70 70 70 70
Net requirement 80
Planned Order
Receipt 90
Planned Order
Release 90
Following the material requirements plan (MPR) for B.
Item B 1 2 3 4 5 6 7
Gross 320
Requirement
On-hand = 100
Schedule reciept
Balance 100 100 100 100
Net requirement 220
Planned Order
Receipt 220
Planned Order
Release 220
Following the material requirements plan (MPR) for component C; we have:
Item C 1 2 3 4 5 6 7
Gross 440 270
Requirement
On-hand = 30
Schedule reciept 20
Balance 50 50
Net requirement 390 270
Planned Order
Receipt 390 270
Planned Order
Release 390 270