One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z, 70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units of component C in week 4. Lead times are two weeks for Z and B, and one week for the other components. Lot-for-lot ordering will be used for all items.

Respuesta :

Answer:

Explanation:

From the question; in regard with the material requirements plan MRP for the item Z; we have the following constructed table:

Item Z                       1            2           3           4            5        6          7      

Gross                                                                                                  120

Requirement                                                                                            

On-hand = 40                                                                                          

Schedule reciept                                                                                    

Balance                  40         40            40          40        40      40        -  

Net requirement                                                                                   80  

Planned Order

Receipt                                                                                                   80    

Planned Order

Release                                                                             80                        

Following the material requirements plan (MPR) for A.

Item A                       1            2           3           4            5        6          7      

Gross                                                                             160                    

Requirement                                                                                            

On-hand = 70                                                                                          

Schedule reciept                                                                                    

Balance                  70         70            70        70                                  

Net requirement                                                                                   80  

Planned Order

Receipt                                                                             90                      

Planned Order

Release                                                                             90                        

Following the material requirements plan (MPR) for B.

Item B                       1            2           3           4            5        6          7      

Gross                                                                             320                    

Requirement                                                                                            

On-hand = 100                                                                                          

Schedule reciept                                                                                    

Balance                  100      100         100         100                                  

Net requirement                                                            220                    

Planned Order

Receipt                                                                          220                      

Planned Order

Release                                               220                                                

Following the material requirements plan (MPR) for component  C; we have:

Item C                       1            2           3           4            5        6          7      

Gross                                                 440       270                                  

Requirement                                                                                              

On-hand = 30                                                                                              

Schedule reciept     20                                                                                

Balance                  50      50                                                                      

Net requirement                                 390       270                                        

Planned Order

Receipt                                                390       270                                        

Planned Order

Release                               390       270