Marv Company's direct labor costs for manufacturing its only product were as follows for October: Standard direct labor hours (DLHs) per unit of product 2 Budgeted finished units for the period 7,100 Actual number of finished units produced 5,700 Standard wage rate per direct labor hour (SP) $ 20.00 Direct labor costs incurred $ 234,000 Actual wage rate per direct labor hour (AP) $ 18.00 The direct labor efficiency variance for October, rounded to the nearest dollar, was:


a. $32,000 unfavorable.

b. $20,600 favorable.

c. $26,000 favorable.

d. $3,200 unfavorable.

e. $52,600 unfavorable.