Answer:
Total cost= $3,595
Explanation:
Giving the following information:
Estimated fixed overehad= $155,000
Estimated variable manufacturing overhead= $3.40 per machine-hour
Estimated machine-hours= 50,000
Job A881:
Total machine-hours 100
Direct materials $645
Direct labor cost $2,300
First, we need to calculate the predetermined overhead rate:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= (155,000/50,000) + 3.4
Estimated manufacturing overhead rate= $6.5
Total cost= direct material + direct labor + allocated overhead
Total cost= 645 + 2,300 + (6.5*100)
Total cost= $3,595