Acquisition of Land and Building
On February 1, 2016, Edwards Corporation purchased a parcel of land as a factory site for $100,000. It demolished an old building on the property and began construction on a new building that was completed on October 2, 2016. Costs incurred during this period are:
Demolition of old building $8,000
Architect’s fees 25,000
Legal fees for title investigation and purchase contract 4,000
Construction costs 650,000
Edwards sold salvaged materials resulting from the demolition for $2,000.
Required:
At what amount should Edwards record the cost of the land and the new building, respectively?
If an input box should be blank, enter a zero.
Land Building
Purchase price of land $ $
Demolition of old building
Architect's fees
Legal fees
Construction costs
Salvaged materials
Total

Respuesta :

Answer: The total cost of land will be $110,00 while the total cost of building will be $675,000.

Explanation:

The total cost of land will be $110,00 while the total cost of building will be $675,000. Total cost of land is gotten by ($100,000 + $8,000 + $4,000 - $2,000) = $110,000

Total cost of building is gotten by adding $25,000 + $650,000 = $675,000.

Further explanation has been attached

Ver imagen topeadeniran2