Answer: 0.36
Explanation:
Given the following information :
Hours Wait time = 22.4
Process time = 7.3
Inspection time = 1.9
Move time = 4.5
Queue time = 6.6
The Manufacturing Cycle Efficiency (MCE) equals:
The ratio of the process time and the throughput time
The throughput time (Manufacturing cycle) regers to the duration of time required to manufacture a particular product.
It is usually the sum of the process, inspection, move and queue time.
Therefore, throughput time equals ;
(process + inspection + move + queue) time.
(7.3 + 1.9 + 4.5 + 6.6) = 20.3
MCE = PROCESS TIME / THROUGHPUT TIME
MCE = 7.3 / 20.3 = 0.3596 = 0.36