"Builder Bug Company allocates overhead at $9 per direct labor hour. Job A45 required 4 boxes of direct materials at a cost of $30 per box and took employees 20 hours to complete. Employees earn $15 per hour. Compute the total cost of Job A45."

Respuesta :

Answer:

Total cost =$600

Explanation:

The total cost of the job A45 is the sum of direct material cost, direct labour cost applied overhead .

Direct material cost -(4× 30)=120

Direct labour cost - (20× $15) =300

Overhead  -  $9 × 20 =180

Total cost = 120 + 300 + 180 = $600

Total cost =$600