Answer:
$1,197,658
Explanation:
The computation of Total Cost at activity level of 10,100 Units is shown below:-
Variable Cost per Unit = Variable cost ÷ Number of units
= $919,116 ÷ 9,900
= $92.84
Total Variable Cost at activity level of 10,100 Units = Variable Cost per Unit × Number of units
= $92.84 × 10,100
= $937,684
Total Cost at activity level of 10,100 Units = Fixed cost + Total Variable Cost at activity level of 10,100 Units
= $259,974 + $937,684
= $1,197,658
Therefore we have applied the above formula.