Answer:

Flase.

Explanation:

The plantwide overhead rate method uses multiple rates to allocate overhead costs to products.

False.

As the name indicates, the plantwide overhead rate uses a single rate to allocate overhead. When the predetermined overhead rate is calculated using the activity base method, you have as many predetermined rates as activities.

To calculate a plant-wide overhead rate, you need to use the following formula:

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base