Answer:
a) grilling
b) 12 grilling process per hour
Step-by-step explanation:
the bottleneck in this process is grilling, which slows down production by taking a considerable amount of time.
Grilling takes 5 minutes, which is the longest of any other stage of process
In one hour there are 60 minutes
The hourly rate of grilling is therefore 60/5 = 12 grilling process per hour