Answer:
$138,000
Explanation:
The computation of cost of goods manufactured for July is shown below:-
Cost of goods manufactured for July = Opening work in progress + Direct material + Direct labor + Manufacturing cost - Closing work in progress
= $20,000 + $50,000 + $22,000 + $56,000 - $10,000
= $148,000 - $10,000
= $138,000
Therefore for computing the cost of goods manufactured for July we simply applied the formula.