Answer:
Yancey Productions
1. Predetermined overhead rate = $0.65
2. Computation of the total job cost for "You Can Say That Again:"
Direct materials $1,259,000
Direct labor cost $2,400,000
Overhead cost $1,560,000 ($0.65 * $2,400,000)
Total job cost = $5,219,000
Explanation:
a) Estimates:
Direct labor-dollars to support all productions $8,000,000
Fixed overhead cost $4,800,000
Variable overhead cost per direct labor-dollar $0.05
b) Computation of total estimated overhead costs:
Fixed overhead cost = $4,800,000
Variable overhead = 400,000 ($0.05 * $8,000,000 )
Total overhead cost = $5,200,000
c) Computation of predetermined overhead rate:
Predetermined overhead rate = Estimated overhead costs divided by direct labor-dollars
= $5,200,000/$8,000,000
= $0.65