Answer:
Cost Variance=$50,000
Schedule Variance =$25,000
Explanation:
Calculation for the cost and schedule variances for the project
a. Calculation for Cost Variance
Using this formula
Cost Variance=Earned Value-Actual Cost
Let plug in the formula
Cost Variance = $350,000 - $300,000
Cost Variance=$50,000
b. Calculation for Schedule Variance
Using this formula
Schedule Variance =Earned Value- Planned Value
Let plug in the formula
Schedule Variance = $350,000 - $325,000 Schedule Variance =$25,000
Therefore the cost will be $50,000 and schedule variances for the project will be $25,000