A manufacturing plant operates on one shift basis with 8 hours per shift. In the month of March'20, the number of working days were 26. A Milling machine in this plant was under break-down for 11 working days in March'20 and produced 1200 components in this month.
a. Calculate the utilization of the Milling machine in March'20. (2 Marks)
b. If the designed hourly output of the above Milling machine is 15, then what is the efficiency of the machine?