You work on a concrete crew starting a construction project. Once the pouring begins, it must continue non-stop until it is completed. Your crew will work an 8-hour shift along with two other crews. The total project requires 175,000 yards of concrete. Your supervisor estimates that each crew will pour around 1200 yards per hour. How many consecutive days should you plan to work on this project?

Respuesta :

Answer:

I believe it is 6 days.

The total number of days all crew needs to pour concrete is 6 days consecutive.

Work-day based problem:

What information do we have?

Total number of crew = 3

Total yards = 175,000

Each crew pour concrete per hour = 1200

Total concrete pour per day = 1200 × 3 × 8

Total concrete pour per day = 28,800 yard

Total number of days crew pours concrete = Total yards / Total concrete pour per day

Total number of days crew pours concrete = 175,000 / 28,800

Total number of days crew pours concrete = 6.076

Total number of days crew pours concrete = 6 days

Find out more information about 'Yards'.

https://brainly.com/question/14516546?referrer=searchResults