Respuesta :
The total number of days all crew needs to pour concrete is 6 days consecutive.
Work-day based problem:
What information do we have?
Total number of crew = 3
Total yards = 175,000
Each crew pour concrete per hour = 1200
Total concrete pour per day = 1200 × 3 × 8
Total concrete pour per day = 28,800 yard
Total number of days crew pours concrete = Total yards / Total concrete pour per day
Total number of days crew pours concrete = 175,000 / 28,800
Total number of days crew pours concrete = 6.076
Total number of days crew pours concrete = 6 days
Find out more information about 'Yards'.