you need scheduling a job that needs 3 certified lab technician 12 associates one supervisor paying lab technician 12 per hour the associate 8.5 per hour and supervisor 14 per hour what is the labour cost per week​

Respuesta :

Answer:

$6,080.

Step-by-step explanation:

Since a job requires 3 certified lab technicians, 12 associates and one supervisor, paying lab technicians $ 12 per hour, the associates $ 8.5 per hour and the supervisor $ 14 per hour, to determine the labor cost per week the following calculation must be done:

3 x 12 + 12 x 8.5 + 1 x 14 = X

36 + 102 + 14 = X

138 + 14 = X

152 = X

Thus, the hourly labor cost will be $ 152, therefore, working 8 hours for 5 days a week, the weekly labor cost will be $ 6,080 (152 x 8 x 5).