Answer:
Predetermined Overhead Rate = $11 per labor hour
Explanation:
The predetermined Overhead rate for Stanford Enterprise is calculated by dividing the estimated manufacturing overheads with estimated total direct labor hours.
Actual manufacturing overhead = $302,750
Actual direct labor hours = 27,760 hours
Estimated/ budgeted labor hours = 25,000 hours
budgeted manufacturing overheads = $275,000
Predetermined OH rate = $275,000 / 25,000 = $11 per hour
Actual OH rate = $302,750 / 27,760 hours = $10.91 per hour