Harold works as an operations manager. He uses a project management tool to schedule and manage the steps of the manufacturing process. Harold has made a list of all the activities involved in the process. He has calculated the optimistic time, most likely time, and pessimistic time that the process might take to be completed. Which project management tool is Harold using?
A.
Critical Path Method (CPM)
B.
Program Evaluation and Review Technique (PERT)
C.
Total Quality Management (TQM)
D.
Gantt chart
E.
Just In Time (JIT)

Respuesta :

Answer: B. Program Evaluation and Review Technique (PERT)

Explanation:

Based on the information given, the project management tool that Harold is using is the Program Evaluation and Review Technique (PERT).

Project Evaluation Review Technique is used to determine the time that it'll take to complete a task. It is vital in scheduling of tasks.

Since Harold schedule and manage the steps of the manufacturing process by using a project management tool, the tool used is program evaluation and review technique.

Answer:

b

Explanation:

its right on plato