Mary can do a piece of work in 20 days Malaysia is 25% more efficient than her. the number of days taken by Malaysia to do the same piece of work is ?​

Respuesta :

Answer: 16 days

Explanation:

Given

Mary can do a piece of work in 20 days

Malaysia is 25% more efficient than her. So, she must requires less number of days compared to Mary

No of days Malaysia required

[tex]\Rightarrow \dfrac{20}{1.25}=16\ \text{days}[/tex]