Answer:
½
Step-by-step explanation:
Amount of work A can do in a day: 1/35
Amount of work B can do in a day: 1/140
Amount of work A can do in 14 days: 1/35×14=⅖
Amount of work B can do in 14 days: 1/140x14=1/10
Total amount of work done in 14 days= ⅖+1/10=½