The overhead rate for the assembly department is $37.5 per hour, while the overhead rate for the finishing department is $112.5 per hour.
In business, the overhead rate refers to the production cost of a service or product. This rate is calculated using the following equation:
Based on this, let's calculate the rate for each department:
The manufacturing overhead cost is $960,000
Fishing model: 28 hours x 400 units = 11,200
Yacht: 36 hours x 400 units = 14,400
Total direct labor hours = 11,200 + 14,400 = 25,600
Overhead rate = $960,000 / 25, 600 = $37.5 per hour
Finishing department:
The manufacturing overhead cost is $720,000
Direct labor hours:
Fishing model: 4 hours x 400 units = 1,600
Yacht: 12 hours x 400 units = 4,800
Total direct labor hours = 1,600 + 4,800 = 6,400
Overhead rate = $720,000/ 6,400 = $112.5 per hour
Learn more in: https://brainly.com/question/12928151