Cringe2Win Cringe2Win 09-01-2022 Mathematics contestada Choose the correct answer. The time to complete a project varies inversely with the number of employees. If 6 people can complete the project in 4 days, how long will it take 8 people? A. 5 days B. 3 days C. 2 days D. 6 days