It takes 38 days to build the house for the remaining workers. Since it is said that the total working days for building a house with 8 workers is 20 and 6 workers left after 14 days and each worker is working at the same rate.
Given data:
8 builders can finish a house in 20 days
Each builder works at the same rate
After 14 days 6 builders left.
Calculating the required days:
When 6 builders left after 14 days, 2 builders have remained
Then, we can write
1 builder can finish the work that these 6 builders did in those 14 days is
6×14=84 days
Since it takes 20 days for 8 builders to finish a house, then for 1 builder it takes
1 builder = 20×8=160 days
Then the remaining left for 1 builder to finish the house is 160-84=76 days
Then the remaining 2 builders will build the house in 76/2 days
That is 38 days.
Therefore, the remaining builders build the house in 38 days at the same rate.