Here are the project risk management processes:
1. Identify risks
2. Control risks
3. Perform quantitative risk analysis
4. Plan risk responses
5. Plan risk management
6. Perform qualitative risk analysis

Which of the following is the correct sequence for the project risk management process?

Respuesta :

The correct sequence for the project risk management process according to the PMBOK is:

  1. Plan risk management
  2. Perform qualitative risk analysis
  3. Identify risks
  4. Perform quantitative risk analysis
  5. Plan risk responses
  6. Control risks

What is the project risk management process?

It corresponds to methods and techniques of analysis and management of risks inherent to a project. The objective is to identify negative situations to a project based on the financial, chronological and technological forecast in advance.

Therefore, with project risk management, it is possible to adopt working methods, reducing uncertainties and optimizing the use of available capital.

Find out more about project risk management here: