Respuesta :
Answer:
- No, not enough time
Step-by-step explanation:
Time to complete each of jobs
- 1/2 * 3 = 1 1/2 hrs
- 3/4 * 1 = 3/4 hr
- 1 1/2 * 2 = 3 hrs
- 2 1/2 * 1 = 2 1/2 hrs
Total time at job
- 1 1/2 + 3/4 + 3 + 2 1/2 = 7 3/4 hrs
If the work day lasts for 8 hours, then Lana has only 1/4 hr to travel between jobs and a lunch break.
This time is not sufficient so she can't complete all the jobs.
Answer:
No (see explanation below)
Step-by-step explanation:
Approximate times to carry out each job:
- Mow small lawn = 1/2 hr
- Mow large lawn = 3/4 hr
- Tidy yard = 1 1/2 hr
- Plant annuals = 2 1/2 hrs
For one Saturday, Lana needs to:
- mow 3 small lawns
- mow 1 large lawn
- tidy 2 yards
- plant annuals once
Therefore, the total time for the jobs is:
[tex]\begin{aligned}\sf Total\:time & = \sf 3\:small\:lawns+1\:large\:lawn+2\:tidy\:yards+1\:plant\:annuals\\\\& = \sf 3 \cdot \dfrac{1}{2}+\dfrac{3}{4}+2 \cdot 1 \frac{1}{2}+2\frac{1}{2}\\\\& = \sf 1 \frac{1}{2}+\dfrac{3}{4}+3+2\frac{1}{2}\\\\& =\sf 7 \frac{3}{4}\: hours\end{aligned}[/tex]
The likelihood of Lana being able to complete all the jobs in one day is dependent on how far she needs to travel between jobs and how long she wishes to break for lunch. A typical working day is around 8 hours. Therefore, unless Lana wishes to work for a longer day, it is unlikely she will be able to complete all of the jobs in one day as there is only 15 minutes available for traveling and lunch, which is likely not enough.