Answer:
144 days
Step-by-step explanation:
Let's put the efficiency in terms of b
m = 3b w = 2b b=b
starting with 6 m = 18 b
8w = 16 b
16b = 16 b total 50 b
then increase 12m = 36b
18w = 36b
28b = 28 b total = 100 b
You doubled 'b' workers so work time will be halved to 144 days