Respuesta :
Theoretical flow time = 58 minutes
The complete question is
Mamossa Assaf Inc. fabricates garage doors. Roofs are punched in a roof punching press (15 minutes per roof) and then formed in a roof forming press (8 minutes per roof). Bases are punched in a base punching press (3 minutes per base) and then formed in a base forming press (10 minutes per base), and the formed base is welded in a base welding machine (12 minutes per base). The base sub-assembly and the roof then go to final assembly where they are welded together (10 minutes per https://brainly.com/question/27786618garage) on an assembly welding machine to complete the garage. Assume one operator at each station.
Roof → Roof - punch(15 min) → Roof-form(8 min) →→→→→→→→↓
(10)Assembly→ Door
Base → Base - punch(3 min) → Base - form(10 min) → weld(12 min)↑
Roof path = 15 + 8 = 23
Base path = 3 + 10 + 12 =25
Theoretical flow time = Roof path + base path + assembly = 23 + 25 +10 = 58 mins
To learn more about Theoretical flow time :
https://brainly.com/question/27786618
#SPJ4