if the work remaining is greater than the time remaining, the critical ratio (cr) will be group of answer choices less than one. greater than one. none of these answer choices is correct. equal to one.

Respuesta :

The critical ratio (cr) will be less than one if the amount of work left is larger than the amount of time left.

The crucial ratio is a guideline used in a work centre to prioritise tasks that need to be processed (CR). The CR priority index number is calculated by dividing the remaining shop time by the formula (due date - today's date). The work with the lowest CR is scheduled first when sequencing based on these factors. A dispatching rule that divides the time left before the due date by the anticipated amount of time needed to complete the task to arrive at a priority index number. Ratios below 1.0 are typically considered to be behind schedule, whereas ratios above 1.0 are considered to be ahead of plan. Critical ratio (CR) = CPI x SPI

To read more about critical ratio, visit https://brainly.com/question/29574348