find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an ev of $535,000

Respuesta :

Profitability index is 0.0102, while schedule performance measure is 0.0099.

What is an example of cost variance?

A cost variation, in general, is the discrepancy between a cost's actual number and its intended or budgeted amount. For instance, a corporation would have a cost variation of $150 if actual repairs costs for May were $950 as opposed to the $800 projected amount.

What causes variations in costs?

The authors of the budget could make mistakes as they are putting the approach together.

PV = $540,000

EV = $535,000

AC = $523,000

Cost variance = EV-AC

=$535,000 - $523,000

= $120,00

Schedule variance = EV-PV

=$535,000-$540,000

= - $5,000

Cost Performance Index= EV/AC

=$535,000/$523,000

=1.02% or 0.0102

Schedule Performance Index= EV/PV

=$535,000/$540,000

=0.99% or 0.0099

To know more about cost variance visit:

https://brainly.com/question/15078977

#SPJ4