A dependency is a trigger that enables a project manager to close the project before completion. The statement is false.
In project management, a dependencey is a collection of connected activities. In project management, dependencies can take many distinct forms: Finish-to-Start: Task A must be finished before Task B may begin. Start-to-Start: Prior to job A starting, task B cannot begin.
A dependency is a logical relationship that exists between the projects tasks, or between a project task and milestone.
Kill switch is a trigger that enables a project manager to close the project before completion.
Hence, False is an appropriate response.