After a re-evaluation of the duration of activity B, it has been provided the following data. Most likely duration = 10 Optimistic Duration = 16 Pessimistic Duration = 25 Using the three-point estimating technique the new duration of activity B is a. 7 b. 15 c. 17 d. 22