A certain project has ten activities. two activities each have a total slack of 5 days. the total duration of the projects critical path is 40 days. the duration of the project is ________.

Respuesta :

The slack time is the difference between the critical path and the duration of the paths taken. In this case, we are given the slack time of 2 activities and the number of days of the critical path. The total duration of the project hence is 5*2 + 40 days = 50 days.