A company has determined that the standard for labor is 2 hours per unit at $10 per hour. If a process produces 10,000 units and uses 2.8 hours at $9 per hour, the labor efficiency variance is
a) $14,000 unfavorable
b) $12,000 favorable
c) $14,000 favorable
d) $12,000 unfavorable